AAA Self Storage Depot 600
Brooksbank Ave N. Vancouver, BC V7P3T4 See
photo gallery AAA Self Storage Depot
was the first project that Diamondback Metal Systems completed in Vancouver, BC.
This was over 100,000 square foot 3-story building. This project was very challenging
for Diamondback in the design aspect due to most of the self-storage facilities
built in Canada are constructed mostly in heavy steel components. This took many
meetings with city officials and the structural engineer to devise a system that
not only incorporated heavy steel components it also included a light guage post
and purlin design. The 1st and 2nd floor used heavy steel components while the
3rd floor was light guage components. Through out the whole process there were
several design changes due to city requirements, but Diamondback Metal Systems
over came all of the changes that were placed in front of them while working closely
with the structural engineer and the General contractor involved in this project.
Palcor Management was the General Contractor on this project, and provided the
erection of this facility. AAA
Self Storage Depot 1175
West 1st St. N. Vancouver, BC V7P3T4 (photos
not available at this time) AAA Self
Storage Depot was a 97,000 square foot 3-storage building located in Vancouver,
BC. Since this was the 2nd facility working with the same owner, structural engineer,
and general contractor the design of the building was less complicated on this
building. Many of the design changes that were made on the 1st building were incorporated
early into the design of this building. The 1st and 2nd floor consisted of heavy
steel components, and the 3rd floor used a light guage post and purlin system.
The only challenges on this project were due to the winter weather conditions
in Canada. AAAABCO
Self Storage 6672 Boulder Hwy Las Vegas, NV 89122 See
photo gallery AAABCO Self Storage
was a 72,400 square foot facility which consisted of 1 single-storage building
and 2 multi-storage buildings. This project started in February 2006 and construction
was completed in June 2006. This was an addition to an existing facility which
meant that certain color schemes and building designs needed to match. Diamondback
Metal Systems supplied the metal building components on this project, and Diamondback
Installations erected the buildings along with the door and hallway components.
Airport Resort
Parking LLC 7779 Harry B. Combs Pkwy Denver, CO 80249 (photos
not available at this time) Airport Resort
Parking was an addition to an existing facility. Diamondback Metal Systems supplied
the material for 8 additional units, while Diamondback Installations erected the
units. This site is located next to the Denver Airport and these units are sold
to individuals to park their cars while they are traveling. Akamai
Self Storage 91-923 Fort Weaver Rd. Ewa Beach, HI 96706 See
photo gallery 
Akamai
Self Storage is a 104,000 square foot facility located on Ewa Beach, HI. This
project started in the Fall 2005 and construction was completed in Spring 2006.
The 3- story self storage facility was installed with a firewall insulated panel
with an Asteco finish. Diamondback Metal Systems supplied and installed all of
the door and hallway components for the facility, and Diamondback Installations
provided the erection for this project. Akamai
Self Storage consists not only of an office facility, but includes an apartment
for housing its resident managers. Since the facility opened in the Spring of
2006 their projected lease up is on schedule per their projections. This facility
won Facility of the Year in the Messenger Magazine. Anacortes
Self Storage 3825 S. Ave. Anacortes, WA 98221 See
photo gallery Anacortes
Self Storage was a 22,300 square foot facility which consisted of 2 single-story
buildings. Due to heavy rain in the Washington are this project was delayed for
over a month. This projected started in January 2006 and was completed in March
2006. Diamondback Metal Systems did not supply the material on this job, but Diamondback
Installation provided the erection of the 2 buildings. Bayview
Clearspan Bayview Rd. Anacortes, WA 98221 (photos
not available at this time) Bayview Clearspan
was a 6,000 square foot clearspan metal building. This project started in November
2005 and was completed in December 2005. Due to high wind conditions the installation
crews were delayed working on several areas of the building, due to safety concerns.
Diamondback Metal Systems did not supply any material for this building, but Diamondback
Installations provided all of the erection for constructing this building. Belmarin
Keys Self Storage 455 Belmarin Keys Blvd. Novato, CA 94949 (photos
not available at this time) Belmarin
Keys Self Storage is a 89,500 square foot building. This project consists of 2
single-story and 3 multi-story buildings. This facility not only includes conventional
storage but wine storage and an office with a resident manager living area. This
project started in Winter 2005 and completed in Summer 2006. Diamondback Metal
Systems supplied the materials for the buildings which included the door and hallway
components. Diamondback Installations supplied the labor to erect the buildings
for this facility. C
& T Damms Storage 6740 Lake Isabella Blvd. Lake Isabella, CA 93240 (photos
not available at this time) C & T
Damms Storage was 4 single story buildings. This project started in May 2006 and
was completed in June 2006. Diamondback Metal Systems did not supply any material
on this jobsite, but Diamondback Installations provided all of the erection for
constructing this building. Discovery
Park Self Storage 1470 King St. Bellingham, WA 98229 See
photo gallery 
Discovery
Park Self Storage is a 48,000 square foot facility located in Bellingham, WA.
This project started in July 2005 and construction was complete in December 2005.
This is a 4-story self storage facility that was constructed out of an all steel
frame structure. Diamondback Metal Systems not only supplied and installed all
of the building components, but all of the door and hallway systems for the facility.
This is a 26ga corrugated hallway system
with rollup doors and filler corrugated filler panels. In this system the options
of kick plate and corner guards were utilized to give added protection to very
high traffic areas in the hallway system. This also incorporates a soffit light
system for added visibility in the hallways. This
is a double stack locker unit which is good for wine storage customers or customers
not needing much space to store their items. These are prehung doors with no exposed
screws. This system comes in a single, double or triple stack system depending
on your customers needs. Hawaii
Self Storage Pearl City Honolulu, HI (photos
not available at this time) Hawaii Self
Storage, owned by MW Group, made some unit mix changes to their existing facility
in Pearl City, HI. Since Diamondback Metal Systems and Diamondback Installations
were currently working on a jobsite in Hawaii it was easy to accommodate supplying
door and hallway components for their facility. Hawaii
Self Storage Waialea 2909 Waialea Ave. Honolulu, HI 96816 See
photo gallery Hawaii Self Storage
is a 120,000 square foot building. This facility is a multi-story building consisting
of 5 floors. This project started in April 2006 and was completed October 2006.
The biggest challenge for Diamondback Metal Systems and Diamondback Installations
were the material deliveries and storing the material onsite. The site was on
the corner of 2 major roads in Honolulu and for every delivery the city had to
close the roads for the trucks to off load the material. Once the material was
off loaded the space to store the material at the jobsite was very limited. Diamondback
Metal Systems supplied all of the steel building materials along with the door
and hallway components. Leetsdale
Common 6150 E. Leetsdale Dr. Denver, CO 80224 (photos
not available at this time) Leetsdale
Common is a 56,000 square foot building. This facility consists of 2 buildings,
this was an addition to an existing facility. This project started in November
2006 and was completed in December 2006. Diamondback Metal Systems provided all
of the metal building components along with the door and hallway components. Diamondback
Installations provided the erection for this project. Lockaway
Self Storage 12176 Locust Ave. Victorville, CA 92329 See
photo gallery 
Lockaway
Self Storage is a 20,910 square foot facility which consists of 2 single story
buildings. This project started in May 2005 and was completed in July 2005. This
was an existing facility that they were expanding, so there were certain items
that needed to be consistent with the current buildings. There were some additional
items that the owner asked Diamondback Installations if they could help him complete
and the crews came back a few weeks later to accommodate the owners request. Diamondback
Metal Systems and Diamondback Installations are currently working on another project
for this owner. Main
Street USA Self Storage 1430 North Norma St. Ridgecrest, CA 93556 (photos
not available at this time) Main Street
USA Self Storage was a 10,900 square foot facility which consists of 2 single-story
buildings. This project started in the beginning of June 2005 and was completed
at the end of June 2005. This project had several delays due to high wind conditions
which our installation crews were not allowed to work due to safety conditions.
Diamondback Metal Systems designed this facility and Diamondback Installations
supplied all of the erection to the buildings. Meridian
Self Storage 170 E. Baker View Bellingham, WA 98226 See
photo gallery Meridian Self Storage
is a 34,000 square foot building. This facility is a multi-story building consisting
of 4 floors. This project started in September 2006 and was completed in December
2006. Weather delays stopped the installation of this project several times. Diamondback
Installations provided all of the erection for this facility which included the
steel building components along with the door and hallway components. N.
Main Self Storage 1280 N. Main St. Manteca, CA (photos
not available at this time) N. Main Self
Storage was a 19,200 square foot facility which consisted of 2 single-storage
buildings. Diamondback Metal Systems supplied engineered drawings and material
for this project, and Diamondback Installations supplied all of the erection for
these buildings. This project started at the end of August 2005 and was completed
in the middle of September 2005. North
Plains RV & Self Storage 29785 NW West Union North Plains, OR 91733 (photos
not available at this time) North Plains
RV & Self Storage is a 80,450 square foot facility which consists of 9 single
story buildings. This project started in October 2006 and was completed in February
2007. Due to the extreme weather conditions hitting the Northwest area there were
several delays on this jobsite. Diamondback Metal Systems supplied a post and
purlin system for framing the buildings and a complete door and hallway system
for the buildings. On this project there were several commercial grade doors with
motorized operators which were required for complying with ADA requirements. Diamondback
Installations provided all of the installation for these materials.
Public
Storage Reroof 3436 N. Sinton Rd. Colorado Springs, CO 80907 (photos
not available at this time) Public Storage
Reroof consisted of reproofing 5 buildings. This project started in November
2006 and took approximately 2 weeks to complete. We are seeing more of this type
of work being performed as some of the existing facilities were built many years
ago and need to be replaced. The metal building manufacturers have made many improvements
over the years to make the roofing material much more durable and longer lasting. Put
It In Storage 300 Pinkerton Dr Woodland, WA 98674 (photos
not available at this time) Put It In
Storage is a 128,115 square foot facility. This project consists of 12 single
story buildings. Diamondback Installations started erecting in November 2006 and
will be completed in February 2007. Diamondback Metal Systems provided all of
the metal building components along with the door and hallway components. Several
commercial grade doors with motors were supplied on this job to comply with the
ADA requirements in this area. Red
Roof Self Storage 7745 N. Virginia St. Reno, NV 89506 (photos
not available at this time) Red Roof
Self Storage is a 55,400 square foot facility. This project started at the end
of October 2006 and was completed in December 2006. Diamondback Metal Systems
supplied all of the material, and Diamondback Installations provided all of the
installation for this project. Revere
Point Mini Storage 5850 Revere Las Vegas, NV (photos
not available at this time) Revere Point
Mini Storage was a material only job supplied by Diamondback Metal Systems. Diamondback
Metal Systems is currently supplying material on another facility for this owner. Safeguard
Self Storage 6th St. Victorville, CA (photos
not available at this time) Safeguard
Self Storage was an 81,930 square foot facility which consisted of 8 single-story
buildings. This projected started in April 2005 and was completed in August 2005.
This was a labor job only and Diamondback Installations supplied all of the erection
for the buildings. Shurgard
Storage 10455 Irma Dr. Northglenn, CO 80233 (photos
not available at this time) Shurgard
Storage is a 32,600 square foot facility. This project consists of 1 single story
building and 1 multi-story building which contains 3 floors. This project started
in October 2006 and was completed in January 2007. Diamondback Metal Systems supplied
all of the metal building components along with the door and hallway components.
Diamondback Installations provided all of the erection for this project. Shurgard
Storage 10299 SW Barbur Blvd Portland, OR 97219 (photos
not available at this time) Shurgard
Storage is a 58,050 square foot facility. This project consists of 1 multi-story
building which contains 3 floors. This project started in July 2006 and was completed
in December 2006. Diamondback Metal Systems provided all of the metal building
components for this facility, and Diamondback Installations provided all of the
erection for this project. Shurgard
Storage 14900 Aurora Ave. N Shoreline, WA 98133 See
photo gallery Shurgard Storage is
a 47,975 square foot facility. This project consists of 1 multi-story building
which contains 4 floors. This project started in January 2006, and due to several
weather delays, the project was completed in August 2006. Diamondback Metal Systems
provided all of the metal building components for this facility, and Diamondback
Installations provided all of the erection for this project. Simply
Storage of HI 500 Ala Kawa St. Oahu, HI (photos
not available at this time) Simply Storage
of HI is a 31,482 square foot facility. This project was an existing clear span
building. This project started in April 2006 and was completed in September 2006.
Since this was a clear span building a mezzanine floor system needed to be constructed
to provide the 3 floors needed to accommodate the unit mix designed by the Architect.
The first 2 floors required structural metal building framing components while
the 3rd floor was a free standing system. Diamondback Metal Systems provided all
the metal building components and door and hallway components for this facility.
Diamondback Installations provided the erection for this project. Storage
Depot 140 Hopkins Corvallis, OR See
photo gallery 
Storage
Depot 35,000 square foot expansion located in Corvallis, OR. This expansion consists
of 2 single story buildings. The project started in July 2005 and construction
was completed in September 2005. Diamondback Metal Systems provided all of the
steel framing for this facility, and Diamondback Installations provided the erection
for this project. This facility allows tenants to drive up directly to their unit
for easy accessibility. Super
Space Storage II 515 W. 132nd. St. Los Angeles, CA 90248 (photos
not available at this time) Super Space
Storage II is a 71,220 square foot facility. This project consists of 1 multi-story
building which has 2 floors. This project started in May 2006 and was completed
by November 2006. Diamondback Metal Systems supplied all of the metal building
components, while Diamondback Installations provided all of the erection for this
project. Thunderbird
Self Storage 14800 N. 83rd Ave. Peoria, AZ 85381 See
photo gallery 
Thunderbird
Self Storage is a 134,000 square foot facility located in Peoria, AZ. The project
started in October 2005 and construction was completed in February 2006. This
facility consists of 2 single story buildings and 2 ‚ 2 story buildings. Diamondback
Metal Systems provided all of the light gauge framing for this project. This single
story building allows for easy access so that the customer is able to drive directly
up to their unit. |